26 August 2008

FIRE CREWS CALL FOR URGENT INVESTIGATION INTO SOARING COSTS OF FIRE SERVICE IT PROJECT

Plans to close 46 emergency fire control rooms in England and move to 9 regional centres will cost £868 million, not the £100 million originally budgeted, nor the £360 million which the Government currently claims, the Fire Brigades Union has learned.

The £868 million includes £278 million of spending on management consultants, regional project directors, “change co-ordinators”, project assurance directors, PR staff, civil servants, and agency staff. “There is an army of management consultants, contractors and employment agencies swimming in taxpayer’s cash,” said FBU general secretary Matt Wrack.

The project, called Firecontrol, is already three years late, with no guarantee it will work as claimed. The Government originally promised massive savings and that the project would pay for itself within 5 years.

The Fire Brigades Union is calling for an urgent investigation into the controversial plans. The plans affect every fire service in England, although similar plans were recently dropped in Scotland and have not been considered in Wales.

The union accuses the Government of diverting massive amounts of public money away from frontline fire services where it is desperately needed. It says the Project, known as Firecontrol, is unnecessary, over budget and three years late.

Only £190 million, less than a quarter of the costs identified, will be spent on the actual technology. The costs also include nearly £400 million for renting new buildings.

The union has identified the £868 million of costs from the detail of a series of parliamentary answers and Department for Communities and Local Government circulars. But the union expects the much delayed national business case will show project costs in excess of £1.5 billion.

The union’s research shows:

+ £92.2 million has been ear-marked for regions and fire brigades to pay largely for additional staffing and associated projects costs between 2008 and 2011 including for regional directors, press officers, “change co-ordinators”, project assurance staff and for “redundancies, relocation and redeployments”.

+ £55.4 million going to management consultants, well above the last estimate of £36 million. By the end of June of this year, £38,571,512 had already been paid with a further £16.9 million more ear-marked for consultants by the end of the project.

+ £27, 885,926 was paid between 2005 and 2008 to fire brigades and regions to cover the additional staffing and associated costs of setting up the project.

+ £22 million had been paid by the Department until the end of June 2008 on those working on the project at national level including civil servants, contractors and agency staff (in addition to consultants).

These four sets of costs alone come to a total of £278,860,956 and still rising, mainly for staffing and associated costs. This figure is nearly three times the original cost estimate of £100 million for the entire project.

In addition there are rental costs for the new 9 regional control centre buildings of at least £342 million, which excludes London. FBU researchers conservatively estimate the lease for a new regional control centre in London will cost £60 million, pushing the rental cost of the buildings for the new national network above £400 million.

The IT system costs regularly quoted in Parliamentary Answers are only £190 million. The union believes that cost is actually £213 million for the first 8 years alone.

FBU general secretary Matt Wrack said: “The public and the fire service are being taken to the cleaners. There is an army of management consultants, contractors and employment agencies swimming in taxpayer’s cash.


“We’re short of firefighters in many brigades and in desperate need of more safety critical equipment and training. Even a fraction of this money would make an enormous difference in every fire brigade.

“Instead, it is being wasted on management consultants, regional project directors, change co-ordinators, project assurance directors, PR and human resource directors. No one ever dialled 999 and asked for any of those.

“It is an appalling waste of public money on a project which is unnecesary, already three years late, massively over budget and with no guarantee it will work as claimed. The Government’s track record of major IT-based projects is truly appalling and this is underlined by what is happening in the fire service.

“There must be an urgent independent review into what is going on with this project before it is too late. The Government thinks the project is going along splendidly, when almost everyone else in the fire service knows it is already a disaster.”

***ENDS***

Media contacts

National Francis Beckett 020 8349 9194 / 07813 001372

East Anglia Adrian Clarke 07917 017713

North West Kevin Brown 07834 656085

North East Pete Wilcox 07977 006 132

South West Tam McFarlane 07813 170 279

South East

For Berkshire, Buckinghamshire, Hampshire, Isle of Wight and Oxfordshire contact:- Karl Horan 07917 065856

For Kent, Surrey, East and West Sussex contact:- Jim Parrott 07702 394440

Yorkshire & Humberside Sean Cahill 07968 071849

West Midlands Chris Woods 07788 700 675

East Midlands

Tom Murray - Regional Control Rep 07894613403

Phil Poole – Regional Control Rep 07894613397

Dave Limer – Regional Secretary 07894 613404

Northern Ireland Jim Barbour 07711 210731 / Jim Quinn 07788 700 675

Scotland Roddy Robertson 07801 047601 / Ken Ross 07801 047602

Wales Mike Smith 07702 285514 / Grant Mayos 07970 475153

Sources quoted below in full, where possible.

Source 1: £92 million ear-marked for local brigades and regions 2008 to 2011:

2 Jun 2008 : Column 542

Robert Neill: To ask the Secretary of State for Communities and Local Government (1) what effect she estimates the FiReControl project will have on the council tax precept on individual fire and rescue authorities over the next three years; [207525]

(2) what funding has been set aside by her Department to finance any new burden costs associated with the implementation of regional control centres; [207527]

(3) what liability or financial burden fire and rescue authorities will bear for any cost overruns in delivery of the FiReControl project; [207532]

(4) what changes will be made to the funding of fire and rescue authorities as a consequence of the FiReControl project. [207533]

Mr. Dhanda: The FiReControlProject should have no impact on council tax precepts for Fire and Rescue Authorities. In line with the Government's commitment on new burdens, a specific grant of £92,200,000 has been allocated to cover the net additional cost to Fire and Rescue Authorities of the FiReControlProject over the period of the Comprehensive Spending Review 2007. Any cost overruns in the delivery of the project will be met by Communities and Local Government.”

The relevant Fire Service Circular FRS circ 5/2008, FiReControl Implementation Funding Circular sets out the details and what the funding is for (largely extra staffing and associated costs, but also a small amount of other costs). The figures actually add up to £92.9 million, rather than the £92.2 million quoted in the Parliamentary Answer above.

The relevant part of the circular includes:

“CSR 07 Funding covering the three Financial Years 2008-09 to 2010-11

4.1 The Department intends to provide the following funding during the CSR07 Period.

FY 2008-09

FY 2009-10

FY 2010-11

£27.0m

£36.6m

£29.3m

4.2 These funds are intended to cover the following:

Transition activities – as set out in the FRS transition plans;

Staff Pool – the estimated costs of the staff pool currently being explored with the East Midlands, North East, South West and West Midlands;

LACC companies – all costs prior to cutover, including staff and accommodation costs, professional advice and insurance;

Regional Project Teams – the cost of regional project teams, local FRS change co-ordinators and project assurance;

Specific one-off staff costs – redundancies, relocation and redeployments.”

Source 2: £54.4 million going to consultants:

John McDonnell: To ask the Secretary of State for Communities and Local Government what her estimate is of the cost, including VAT, of all consultants' fees for the FiReControl project for the duration of the project. [217129]

Mr. Dhanda[holding answer 8 July 2008]: To the end of June 2008 the cost of consultancy services for the FiReControl project totalled £38.6 million (inclusive of VAT). Communities and Local Government estimate that future costs will be £16.9 million (inclusive of VAT).

Source 3: £27.8 million has already been allocated for the FireControl Project by the Department and spent by fire brigades and regions:

PQ 20 March 2008: Mr. Drew: To ask the Secretary of State for Communities and Local Government what allocation was made to each fire authority for (a) fire control, (b) fire link and (c) new dimensions programmes in each year since 2002, broken down by region. [195408]

Mr. Dhanda: The information requested is listed in the following tables.

Fire control—Grants to fire and rescue authorities

£

Fire and rescue authority

2005-06

2006-07

2007-08

Bedfordshire and Luton Combined Fire Authority

11,616

76,984

111,904

Cambridgeshire and Peterborough Fire Authority

11,170

80,366

118,157

Essex Fire Authority

15,411

92,742

132,170

Hertfordshire County Council

11,839

82,412

117,039

Norfolk County Council

193,796

216,233

331,130

Suffolk County Council

11,616

79,425

115,043

East of England Total

255,448

628,162

925,443

 

 

 

 

Derbyshire Fire Authority

28,179

158,096

613,165

Leicester, Leicestershire and Rutland Combined Fire Authority

222,125

335,943

2,157,403

Lincolnshire County Council

28,416

148,068

525,606

Northamptonshire County Council

26,589

144,838

269,849

Nottinghamshire and City of Nottingham Fire and Rescue Authority

29,006

159,421

525,225

East Midlands Total

334,315

946,366

4,091,248

 

 

 

 

Greater London Authority

87,571

234,150

659,062

London Total

87,571

234,150

659,062

Cleveland Fire Authority

219,699

325,541

1,193,418

County Durham and Darlington Fire and Rescue Authority

31,227

142,711

293,546

Northumberland Fire Authority

28,814

131,633

248,152

Tyne and Wear Fire and Rescue Authority

33,948

160,944

388,365

North East Total

313,688

760,829

2,123,481

 

 

 

 

Cheshire Fire Authority

15,230

93,692

177,393

Cumbria County Council

12,998

85,963

128,299

Greater Manchester Fire and Rescue Authority

243,923

118,093

283,347

Lancashire Combined Fire Authority

19,025

99,611

224,957

Merseyside Fire and Rescue Authority

21,257

239,612

465,158

North West Total

312,433

636,971

1,279,154

 

 

 

 

Buckinghamshire and Milton Keynes Fire Authority

11,231

95,538

135,765

East Sussex Fire Authority

11,555

99,159

143,632

Hampshire Fire and Rescue Authority

14,705

112,472

320,891

Isle of Wight Council

10,779

87,619

123,409

Kent and Medway Towns Fire Authority

15,573

115,410

296,981

Oxfordshire County Council

11,141

94,284

143,810

Royal Berkshire Fire Authority

13,671

97,139

157,406

Surrey County Council

11,555

104,084

143,551

West Sussex County Council

218,713

234,415

382,295

South East Total

318,923

1,040,120

1,847,740

 

 

 

 

Avon Fire Authority

33,082

52,986

462,041

Cornwall Fire and Rescue Authority

28,588

52,986

56,041

Devon Fire and Rescue Authority

33,732

188,818

Devon and Somerset Fire and Rescue Authority

46,559

2,899,563

Dorset Fire Authority

52,986

56,041

Gloucestershire County Council

29,834

52,986

1,114,041

Somerset Fire Authority

29,794

724,619

Wiltshire and Swindon Fire Authority

195,455

52,986

56,041

South West Total

397,044

1,178,367

4,643,768

 

 

 

 

Hereford and Worcester Fire Authority

71,277

148,228

319,276

Shropshire and Wrekin Fire and Rescue Authority

11,375

137,554

269,128

Stoke-on-Trent and Staffordshire Fire and Rescue Authority

15,626

161,277

331,032

Warwickshire Fire and Rescue Authority

10,803

138,902

256,054

West Midlands Fire and Rescue Authority

166,056

357,304

785,796

West Midland Total

275,137

943,265

1,961,286

 

 

 

 

Humberside Fire Authority

14,799

83,956

123,024

North Yorkshire Fire and Rescue Authority

12,541

84,736

124,080

South Yorkshire Fire and Rescue Authority

16,828

88,617

170,161

West Yorkshire Fire and Rescue Authority

201,302

239,954

531,957

Yorkshire and Humberside Total

245,470

497,263

949,222

 

 

 

 

FireControl Total

2,540,029

6,865,493

18,480,404

Source 4: £22 million spent national by the Department on civil servants, contractors and agency staff:

John McDonnell: To ask the Secretary of State for Communities and Local Government what the (a) staffing costs, including civil servants, interim and agency staff, (b) secondment costs and (c) travel costs of the national FiReControl project team have been; and whether these costs are included in the business case. [R] [217126]

Mr. Dhanda[holding answer 8 July 2008]: The following table identifies the costs incurred on FiReControl to the end of June 2008.

Resource type

Total (£)

T and S

1,176,773

Pay, civil servants

4,824,300

Interim (including fixed term contractors and agency staff)

11,692,568

Secondee

4,328,853

Total

22,022,494

These costs were included in the Business Case version 1 published in June 2007 and will be updated in part 2 of the Business Case to be published later in the summer. A copy of the full Business Case will be placed in the Library.

Source 5: Regional control centre rental costs in excess of £400 million.

The parliamentary answer quoted below establishes the agreed rents of the new regional control centres will cost £342 million nationally. But this excludes the cost of leasing London’s new regional control, which we conservatively estimate at £60 million, and takes no account of the varying leasehold lengths of 25 and 20 years which will cost additional money for the extra 5 years of leasing required.

Parliamentary answer 13 March 2007

Mr. Drew: To ask the Secretary of State for Communities and Local Government what estimate she has made of the rental cost of each regional fire control centre, over the full period of its lease, inclusive of VAT and increases produced by the mechanism for future regular rental upratings. [126285]

Angela E. Smith: The rental costs of each Regional Control Centre (RCC) are shown in the following table. The costs given are over the full period of the lease, inclusive of VAT and uplifted in line with the terms of the lease. The costs, other than for London, are based on rents agreed with the developer of each RCC. Procurement of the London RCC is in progress. RCCs should be able to recover the VAT.

RCC

Estimated cost (£ million)  

Lease term (years)

East Midlands

45

25

East of England  

50

25

North East  

31

20

NorthWest 

45

25

SouthEast 

54

25

SouthWest 

34

20

WestMidlands

50

25

Yorkshire and Humberside

33

20

Source 6: the original estimate of the project was £100 million:

Parliamentary answer 27 October 2005 regarding the original cost estimates for regional fire controls. Then fire minister Jim Fitzpatrick said consultants Mott MacDonald “estimated project costs at £100 million, comprising project management costs, technology costs, accommodation costs and redundancy.”

 